|
South Don
and Flingel Railway |
|
|
Basic
Construction |
|

 |
Construction of the
railway started with about 4 months of reading, investigating, planning
and tearing up of plans. Eventually a basic idea emerged to
incorporate most of my requirements.
Live steam at a
practical scale in a limited space.
A multi-level
railway to provide length of run and interesting driving.
Trackwork
sufficiently robust to stand being walked on.
Plenty of
opportunities to indulge my interest in building structure such as
bridges
The space
available excluded standard gauge and as I prefer the more substantial
look of the 3 foot gauge rather than 2 foot, I opted for 45 mm gauge
track. The need for a robust permanent way pointed me towards LGB
track.
|
|
Contact at:

|
The first phase
track, at ground level, was laid on light-weight building blocks on
concrete and hard core foundations. The track is screwed down and
ballasted with fine stone bought from a local garden centre. In 11
years I have not seen any track displacement due to weather conditions
or ground movement and I am pleased that I chose a relatively heavy
civil engineering solution.
The most significant
error that I made in the initial stages was to lay the LGB flexible
track by pulling it to the required curves and screwing it down.
The forces present at rail joints tends to push the track back to
straight resulting in kinked joints and broken sleepers. I now
pre-bend the rails before assembling and laying the track and this
solves both problems.
The standards
adopted from the start were a minimum of 6 feet radius curves and
gradients 1 in 50 (2%), but as with the best laid plans changes have
been made to the original design and new sections have been added.
In some cases I have had to come down to 5 feet radius and gradients of
about 1 in 40 (2.5%). In my experience there is no need to keep
track level for successful operation of narrow gauge live steam.
|

A visiting Roundhouse
Fowler at our first open day in 1998 |
| |
Raised sections of
track are built on walls of concrete blocks on concrete and hardcore
foundations and act as retaining walls for raised garden plots.
These walls are topped with a row of light-weight building blocks as it
is easier to profile them to the gradients and to fix the track down.
The walls are all hidden behind raised garden areas of a cladding of
stone.
All
points (switches) are operated by pneumatic cylinders from a control box
at Flingel Bunt terminus (also the steaming up area). Air for this
is provided by a compressor kept in the house. The system has
proved to be very reliable, more so now that I have ducted most of the
air pipes to stop local wildlife nibbling at them.
|
 |
| |
One example of major
changes was to remove a shed to give more open space for the garden
railway. Included in this was the construction of a tunnel about
12 feet long, curved and in an incline. Now, how many rules did I
break with that one? |
 
 |
| |
As the trackwork
developed, a friend suggested I have a go at building my own. The
plan started out as a requirement for a pair of points (switches), but
as I worked up the design it evolved into this. The sleepers
(ties) are teak and the rail is LGB brass. It is fitted with four
air cylinders controlled from a single switch so that all blades throw
together. |
 |
| |
The railway has
continued to develop as new ideas have come from experience in running
the railway and in a continuing interest in building structures,
particularly bridges. A visit to what I consider to be the
greatest bridge in the World, the Forth Bridge, prompted me to attempt a
bridge of my own design but in tribute to the Forth Bridge. A
scale model at 1:20.3 scale would have been impossible in the space
available, and so I used the design and rescaled it to fit in the space
available, and in doing so incorporated a slope of 1 in 50 (2%).
The deck is aluminium and the superstructure is PVC.
More pictures can
be found on the Open Days page. |
 |
| |
Further
bridge development is in progress, and opposite are two pictures of the
new bridge under construction. Once again this is not a scale model, but
the design is based on the Tyne Bridge. The structure has a
relatively light-weight look, but is very strong. The deck is
aluminium plate on aluminium angles, the superstructure is PVC and the
hangers are stainless steel bicycle spokes. The plated lower ends
of the main tubes will be set into masonry support towers when the
bridge is set in place in the garden. |
 |
| |
|
 |
| |
Bridge 10
went into service 31 March 2009. As rain was threatening, the
first run across the bridge fell to a battery powered Bachmann
Consolidation |
 |
| |
A need for a
new crossover junction was identified and having lifted 4 points in a
simplification of another part of the railway, it was decided that the
crossover could be made from these by cutting the outer rails. |
 |
| |
I had
intended making the centre of the crossover from rail sections, but a
friend suggested milling it from solid and this looked a good idea. |
 |
| |
The
crossover installed in place of a pair of facing points |
 |
| |
Autumn
2011was chosen to start a series of significant changes to lift and
re-lay the last of the original track, provide more clearance under one
of the bridges to allow a curve to be opened to 6 feet radius, to put in
two new routes, and to rework the terminus station and steam-up area. |
|